Optimalisasi Line Balancing pada Proses Produksi PCB Line KMM-X704KN PT. XYZ

Authors

  • Rahmat Hidayat Universitas Pelita Bangsa
  • Tri Ngudi Wiyatno Universitas Pelita Bangsa
  • Dwi Indra Prasetya Universitas Pelita Bangsa

DOI:

https://doi.org/10.55123/insologi.v5i1.6879

Keywords:

Line Balancing, Helgeson–Birnie, Largest Candidate Rule, Cycle Time, Idle Time

Abstract

This study aims to analyze and balance the production line in the assembly process using two Line Balancing methods, namely Helgeson–Birnie (H-B) and the Largest Candidate Rule (LCR), with a cycle time (CT) set at 2.28 minutes (137 seconds) based on the manual bottleneck workstation. The total element work time was recorded at 19.39 minutes, with a minimum required number of 9 workstations. The calculation results from both methods showed consistent and identical solutions, yielding 10 actual workstations (N_actual = 10). The line performance achieved a Line Efficiency (LE) of 85.04% with a Balance Delay (BD) of 14.96%. Although this efficiency is considered good, idle time analysis revealed a total waste of 3.41 minutes, most of which occurred at Workstation 10, which operated for only 0.20 minutes. These findings indicate that improvements should focus on restructuring the final workstation to eliminate waste, increase LE, and streamline total element time to approach the Takt Time, thereby optimizing overall line performance. This study provides practical recommendations for production management to enhance productivity and the efficiency of the assembly line.

Downloads

Download data is not yet available.

References

Azwir, H. H., & Pratomo, W. H. 2020. “Mplementasi Line Balancing Untuk Peningkatan Efisiensi Di Line Welding: Studi Kasus PT X.” Jurnal Rekayasa 13(3):Azwir, H. H., Pratomo, W. H.

Basuki, A., & Cahyani, A. D. 2024. “Metode Line Balancing Heuristik Untuk Penyelesaian Masalah Terjadinya Bottleneck Pada Lintasan Produksi.” Rekayasa (Jurnal Teknik) 13(3):317–23.

Boysen, N., Fliedner, M., & Scholl, A. 2007. “A Classification of Assembly Line Balancing Problems.” European Journal of Operational Research 183(2):674–93.

Erwanto, I. M., & Adi, P. 2017. “Perbaikan Lintasan CU Dengan Metode Line Balancing.” Jurnal Titra 5(2):387–92.

Juan Rafael Nazareth, Ratna Mustika Dewi. 2025. “Peningkatan Efisiensi Lintasan Produksi Dengan Metode Line Balancing Kilbridge & Wester.” Jurnal Teknik Industri Dan Manajemen Rekayasa (JTIMR) 2(1):17–24. doi: https://doi.org/10.24002/jtimr.v2i1.9306.

Kristianto, A., & Kurniawan, V. R. B. 2015. “Analisa Keseimbangan Lintasan Dengan Menggunakan Metode Helgeson-Birnie (Ranked Positional Weight).” Journal Industrial Services 1(1):97–16.

Ni Luh Ayu Uparina Yanti Putri, I. Ketut Satriawan. 2020. “Analisis Keseimbangan Lintasan Proses Produksi Roti Manis Kasur Kombinasi Di PT. Indoroti Prima Cemerlang.” Jurnal Rekayasa Dan Manajemen Agroindustri 8(4):595–603.

Rachman, T., & Santoso, C. A. 2020. “Penerapan Metode Heuristik Line Balancing Untuk Penentuan Keseimbangan Lintasan Optimal Pada Produksi Sampel Sepatu Di PT. PBI.” JURNAL SIMETRI REKAYASA 2(2):76–85.

Renty Anugerah Mahaji Putri, Wiwik Sudarwati. 2017. “Pengukuran Line Balancing Dan Simulasi ProModel Di PT Caterpillar Indonesia.” Jurnal Integrasi Sistem Industri (JISI) 3(2):15–22. doi: https://doi.org/10.24853/jisi.3.2.%25p.

Sabilah, Ade Irpan. 2025. “Evaluasi Akurasi Metode Westinghouse, Shumard, Dan Performance Rating Dalam Penentuan Waktu Baku Produksi Di CV. B&R Sport Wear.” Jurnal Aplikasi Ilmu Teknik Industri 6(2):69–77. doi: https://doi.org/10.32585/japti.v6i2.7176.

Sivasankaran, Panneerselvam. 2023. “Review on PCB Assembly Line Balancing.” Acta Scientiarum Polonorum Journal 9(2):59–71. doi: 10.22306/atec.v9i2.171.

Sofyan, D. K., Syarifuddin, S., Meutia, S., & Islamiyati, I. 2019. “Penyeimbangan Lintasan Produksi Vulkanisir Ban Dengan Metode Large Candidate Rule (LCR).” Jurnal Rekayasa 13(3):317–23.

Taufiqur Rachman, Crystal Aviantari Santoso. 2019. “Perbandingan Metode Ranked Positional Weight (RPW), Metode Largest Candidate Rule, Dan Metode J-Wagon Untuk Penentuan Keseimbangan Lintasan Optimal Produksi Sampel Sepatu Model SSOW.” Jurnal INOVISI 15(1):9–18.

W. B. Helgeson, D. P. Birnie. 1961. “Assembly Line Balancing Using The Ranked Positional Weight Technique.” Journal of Industrial Engineering 12(6):394–98.

Wardhana, Dimas Rangga. 2019. “Analisis Line Balancing Pada Bagian Sub Frame Motor Matic XXX Menggunakan Metode Rank Positional Weight.” Jurnal Ilmiah Teknik Industri (Jurnal Keilmuan Teknik Dan Manajemen Industri ) 7(3):191–98.

Watkins, R. E. 1995. “A Line Balancing Heuristic Case Study for Existing Automated Surface Mount Assembly Line Setups.” International Journal of Production Economics 40(2):317–329. doi: https://doi.org/10.1016/0360-8352(95)00155-T.

Downloads

Published

2026-02-10

How to Cite

Rahmat Hidayat, Tri Ngudi Wiyatno, & Dwi Indra Prasetya. (2026). Optimalisasi Line Balancing pada Proses Produksi PCB Line KMM-X704KN PT. XYZ. INSOLOGI: Jurnal Sains Dan Teknologi, 5(1), 11–21. https://doi.org/10.55123/insologi.v5i1.6879