Perbandingan Efisiensi Pemakaian Tower Crane dan Mobile Crane pada Gedung Bertingkat

(Studi Kasus : Proyek Rumah Susun Itera TA 2021/2022)

Authors

  • Fara Annisa Darma Putri Insitut Teknologi Sumatera
  • Rajiman Rajiman Insitut Teknologi Sumatera
  • Anita Lestari Condro Winarsih Insitut Teknologi Sumatera
  • Dicky Rahadianto Insitut Teknologi Sumatera

DOI:

https://doi.org/10.55123/insologi.v2i3.2284

Keywords:

Crane, Mobile Crane, Cost and Time, Rumah Susun ITERA

Abstract

A multi-storey construction project requires heavy equipment to support the process of mobilizing materials and materials. The heavy equipment that is often used as a distribution aid when carrying out building construction works are: Tower Cranes and Mobile Cranes. The ITERA RUSUN project uses a Tower Crane as a tool for lifting materials. This study aims to analyze the length of time, the cost and the difference between the time and cost required for Tower Cranes and Mobile Cranes to complete the column pouring work on the fifth floor. In this study, field observations were made with the Tower Crane, while it was used for the Mobile Crane as a comparative tool without field observations. The results of the calculation analysis revealed that the execution time of the pouring work of the fifth floor pillar using a Tower Crane was 6 hours 3 minutes 36 seconds, while the time for the Mobile Crane is 7 hours 17 minutes 24 seconds. The cost of a Tower Crane is Rp. 6,205,000.00 while the cost of a Mobile Crane is Rp. 4,677,000.00. The time difference between using Tower Cranes and Tower Cranes for the pouring work on the fifth floor column is 1 hour 13 minutes 38 seconds with a cost difference of Rp. 1,528,000.00. From the results of the calculations carried out, the use of a Mobile Crane results for casting and material lifting work in terms of costs and savings.

Downloads

Download data is not yet available.

References

Ringsven MK and Bond D. 2016. Gerontology and Leadership Skills for Nurses. 2nd ed. Delmar Publishers, New York. 123-125.

A.Rani, H., 2016. Manajemen Proyek Konstruksi. Viii Ed. Yogyakarta: Deepublish.

Angelina, E., 2019. Analisis Penggunaan Tower Crane Berdasarkan Efektivitas Waktu, Produktivitas Dan Biaya Operasional Pada Proyek The Support To Development Of The Islamic Higher Education. Medan: Program Studi D-Iv Manajemen Rekayasa Konstruksi Gedung Politeknik Negeri Medan

Umum, D. P., 2007. Pelatihan Ahli Muda Pelaksanaan Struktur Bangunan Gedung. Modul Seb-10: Mengenal Peralatan

Akhmad, N. G. P., 2018. Perlindungan Hukum Bagi Pengguna Layanan Jalan Tol Oleh Pt. Jasa Marga (Persero) Tbk Di Jakarta. Skripsi. Program Studi Ilmu Hukum. Universitas Islam Indonesia.

Tamara, O., 2018. Optimalisasi Dan Produktivitas Dari Tower Crane Pada Proyek Caspian Tower Grand Sungkono Lagoon, Jember: Program Studi Teknik Sipil Fakultas Teknik Sipil Dan Perencanaan Universitas Jember.

Syapril Janizar, E. R. S., 2021. Analisis Penempatan Dan Penentuan Jumlah Tower Crane (Tc). Jurnal Teknik Sipil Cendekia, 2(No 2), Pp. 23-34.

Setiawan, G., 2015. Tentang Tower Crane. [Online]

Available At: Http://Gilasipil.Blogspot.Com/2015/11/Tentang-Tower-Crane.Html

[Accessed 20 November 2021].

Ridha, M., 2011. Perbandingan Biaya Dan Waktu Pemakaian Alat Berat Tower Crane Dan Mobil Crane Pada Proyek Rumah Sakit Haji Surabaya. Surabaya: Jurusan Teknik Sipil Fakultas Teknik Sipil Dan Perencanaan Institut Teknologi Sepuluh Nopember.

Arief Hadi Pranata, T. J. W. A. Y. E. P., 2012. Perbandingan Produktivitas Static Tower Crane Dan Mobile Crane Dengan Modifikasi Posisi Supply. Jurnal Teknik Pomits, Volume Vol. 1, No. 1, Pp. 1-6.

Braham Soemartomo, D., 2013. Studi Tentang Pemilihan Jenis Crane Untuk Proyek Bangunan Industri. Surabaya: Universitas Negeri Surabaya.

Santoso, R. P., 2016. Metode Menentukan Jenis Tower Crane Yang Tepat Untuk Proyek Pembangunan Gedung Bertingkat (Studi Kasus Proyek Pembangunan Rumah Sakit Uii Di Yogyakarta). Yogyakarta: Program Studi Teknik Sipil Fakultas Teknik Sipil Dan Perencanaan Universitas Islam Indonesia.

Putra, I. P., 2017. Perbandingan Biaya Dan Waktu Pemakaian Tower Crane Dan Mobile Crane Pada Proyek Pembangunan Rsud Syarifah Ambami Rato Ebu Bangkalan, Surabaya: Jurusan Teknik Sipil Fakultas Teknik Sipil Dan Perencanaan Institut Teknologi Sepuluh Nopember.

Putra, A. E., 2020. Efisiensi Produktivitas Waktu Dan Biaya Alat Berat Tower Crane (Studi Kasus Pada Proyek Apartemen Yudhistira Tower) , Yogyakarta: Program Studi Teknik Sipil Fakultas Teknik Sipil Dan Perencanaan Universitas Islam Indonesia Yogyakarta.

Paulus Eric Hartono, N. R. S. A., 2013. Program Perhitungan Efektivitas Waktu Dan Biaya Pemakaian Tower Crane. S.L.:Program Studi Teknik Sipil Universitas Kristen Petra.

Muhammad Satria Darmawan, P. W. W. T. N., 2016. Produktivitas Mobile Crane Pada Pembangunan Gedung Bertingkat (Studi Kasus Gedung Parkir “B” Proyek Pembangunan Training Centre & Hotel Dpbca, Sentul City, Kab. Bogor). Jawa Barat: Program Studi Teknik Sipil, Fakultas Teknik - Unpak.

Komatsu, M., 2017. Mengenal Dan Belajar Alat Berat Komatsu. [Online]

Available At: Http://Mekanikkomatsu.Blogspot.Com/2017/08/Mengenal-Tadano.Html [Accessed 21 November 2021].

Danutirto, D. T., 2019. Perbandingan Biaya Dan Produktivitas Tower Crane Antara Tipe Potain Fo/23b Dan Xcmg Fo/23b (Studi Kasus : Proyek Pembangunan Gedung Museum Muhammadiyah Di Yogyakarta). Yogyakarta: Program Studi Teknik Sipil Fakultas Teknik Teknik Sipil Dan Perencanaan Universitas Islam Indonesia.

Downloads

Published

2023-06-28

How to Cite

Putri, F. A. D. ., Rajiman, R., Winarsih, A. L. C. ., & Rahadianto, D. . (2023). Perbandingan Efisiensi Pemakaian Tower Crane dan Mobile Crane pada Gedung Bertingkat: (Studi Kasus : Proyek Rumah Susun Itera TA 2021/2022) . INSOLOGI: Jurnal Sains Dan Teknologi, 2(3), 643–656. https://doi.org/10.55123/insologi.v2i3.2284

Issue

Section

Articles